Followings are applicable when procedures based on laws or ordinances, etc. are required.
Name of laws and regulations |
Factory Location Act |
When (The timing of procedures) |
90 days prior to the commencement of construction works for development of factories or offices (in case certain requirements are satisfied, the 90 days can be shorten). |
Who (Procedure Targets) |
Those who newly built factories or offices of 9,000 u or more site area, or 3,000 u or more building area concerning with manufacturing industry, electricity supplying industry, gas supplying industry, or heat supplying industry. (including those who reaches 9,000 u or more site area, or 3,000 u or more building area by the expansion) |
What (Documents) |
Please contact to each municipality.
|
Where (Procedure Office) |
Municipal Section in charge of factory location where the factory or office is located. |
|
|
How (Examination Contents) |
・Production Site Area Ratio (within 35〜65%).
・Green Space-Area Ratio (20% or more).
・Environmental Facilities Area Ratio (25% or more, including green space-areas).
etc. are examined. |
|
|
|
Processing Period |
Approximately 1 month. |